Projects of Transport & Mass Transit Department, Khyber Pakhtunkhwa
| Scheme | Discussion | Decisions | Responsibility |
|---|---|---|---|
| 130525 - Construction of Peshawar Mass Transit System (Bus Rapid Transit) |
ECNEC: (A) Rs. 49.346 billion 10/07/2017 1st Revision ECNEC: (A) Rs. 66.437 billion 14/11/2018 DFC: 31-12-2022 ADP COST Local= 13116.100 Foreign=53321 ADP ALLOCATION =6873.00 1. Representative of TransPeshawar informed the forum regarding physical progress and requested quarterly release of operational expenses. 2. PDA informed revised PC-I is under process subject to ADB concurrence on variation orders. |
1. Chair directed expediting process; Finance Department will consider quarterly releases. 2. PDA to pay attention to BRT and allied infrastructure. |
Additional Secretary and Senior Planning Officer |
| 160147 - Establishment of Transport Inspection Stations in Khyber Pakhtunkhwa |
PDWP:(A) Rs. 216.305 million 26/05/2017 1st Revision PDWP:(A) Rs. 371.960 million 09/01/2019 2nd Revision PDWP:(A) Rs. 394.500 million 22/12/2020 3rd Revision PDWP:(A) Rs. 486.915 million 18/05/2022 DFC: 31-12-2022 ADP COST=486.915 ADP ALLOCATION =116.280 Million Project Director informed that five months salaries have been released. Other liabilities cleared with total expenditure of 23.728 million. |
Case for SNE creation considered in light of Peshawar High Court decision on regularization; hearing on 20.12.2022 | Project Director TIS |
| 150189 - Feasibility Study of Greater Peshawar Region Mass Transit – Circular Rail Road Project |
PDWP:(A) Rs. 72.00 million 03/12/2021 DFC: 30-06-2023 ADP COST= 72.00 ADP ALLOCATION =0.001 KPUMA forwarded the case for onward submission to competent forum; forum agreed to forward along with Minister Transport’s desire. |
1. Administrative Department to submit case to Additional Chief Secretary. 2. Incorporate Minister Transport’s desire in case for appropriate decision. |
Senior Planning Officer, Department of Transport and Mass Transit |